Executive takeaways
- Billed connections and installed connections must remain separate observations; their ratio is not automatically a churn or disconnection rate.
- CNG station additions need station-level throughput and access context before they imply attractive capital returns.
- The best next increment of gas demand may come from activation and utilisation of existing infrastructure, not another expansion headline.
A connected meter is not the same observation as an active bill
PNGRB’s 31 March 2026 snapshot reports 1.69 crore domestic PNG connections and 1.07 crore billed connections. The resulting ratio is roughly 63%, calculated from rounded values. It is a useful activation question, but it is not enough to label the remaining connections as permanently inactive, disconnected or commercially worthless. Reporting periods, billing cycles and the meaning of a billed connection require validation before a causal conclusion is drawn. [S1]
The distinction matters because infrastructure deployment and customer usage have different cost and revenue profiles. A business can incur network and connection expenditure before the customer establishes regular consumption. A strong connection-addition headline can therefore coexist with a slower revenue ramp. The analytical task is to measure the progression from authorised territory to commissioned network, connected customer, first use, recurring billing and sustained volume. Each step needs its own date and definition.
Use the MIS structure to ask the right questions
| Field | What it measures | What it does not establish |
|---|---|---|
| Minimum Work Programme target | Required rollout obligation for the stated period | Delivered demand or actual usage |
| Actual connections / stations | Reported installed or achieved network count | Per-customer or per-station throughput |
| Billed domestic connections | Reported connections associated with billing convention | Permanent retention or lifetime value |
PNGRB monthly CGD MIS separately reports target, achieved and billed fields; interpretation should retain the underlying reporting definitions. [S5]
The October 2025 MIS provides a dated example:15,896,515 domestic connections and 10,046,440 billed connections. Their ratio is approximately 63.2%. Do not interpret its small difference from the rounded March 2026 ratio as a precise performance trend; the snapshots differ in date and rounding, and entity-level changes need reconciliation. Use comparable granular fields if the business decision depends on the direction of activation. [S5]
Segment the demand before making a rollout forecast
A geographical area can contain domestic, commercial, industrial and transport demand with very different load profiles. The IEA’s 2025 outlook gives CGD a prominent role in its growth thesis, but that category-level expectation is not a forecast for every authorised area. A local screen needs the customer mix, alternative-fuel economics, network availability and acquisition cost. An industrial customer may add significant volume while a large number of household meters adds a different commercial and service obligation. [S2]
For domestic PNG, analyse regular consumption and collection rather than counting the first connection as a completed customer journey. For CNG, measure station throughput, operating hours, access, fleet density and the response to competing fuels. For industrial gas, test delivered useful-energy cost and supply reliability. The same customer-growth assumption should not be assigned to all three segments merely because they sit inside one CGD authorisation.
A data model for selecting the next investment
| Decision | Minimum evidence | Useful diagnostic |
|---|---|---|
| Activate existing domestic meters | Billed status over time and regular usage | Activation cohorts, not one total ratio |
| Add a CNG station | Nearby fleet demand, access and station throughput | Volume per station by comparable maturity |
| Develop industrial offtake | Load shape and alternative-fuel comparison | Contribution across delivered-price cases |
| Extend a network spur | Confirmed anchor load and delivery cost | Downside utilisation and staged capex |
| Prioritise collections/service | Billing ageing and issue resolution | Cash conversion alongside reported sales |
Enalyt analytical framework. It does not rank specific GAs or infer undisclosed customer-level performance.
Cohort analysis is especially valuable. Compare customers or stations added in the same period and allow for their ramp-up, rather than interpreting a young asset as a permanently poor performer. Keep commissioning dates and first-billing dates separate. If a region’s count grows while its mature cohort remains stable, the apparent reduction in average throughput may reflect the new denominator rather than deterioration at existing sites.
Where the next unit of intelligence creates value
For a developer, the research question is which bottleneck prevents existing infrastructure from earning: customer economics, physical access, activation, reliability or collection. For a gas supplier, it is which loads remain robust at different delivered prices. For an industrial customer, it is whether the proposed connection produces a competitive and dependable fuel supply. These questions produce more actionable work than a national map coloured entirely by authorisation status.
Build the forecast from the customer cohort upward and reconcile it to reported totals. Show the volume, tariff and cost assumptions separately, and preserve observed versus modelled fields. A transparent activation model can identify where a commercial intervention may work without pretending that every unbilled connection is an immediate sale. That is a more credible B2B discussion than treating network reach as already-realised demand.
A cohort view can make the activation question more actionable. Group connections by the period in which they became available for use, then track billed activity and consumption over comparable elapsed time. Otherwise an area with many newly built connections may look weaker than a mature area simply because its customers have had less time to adopt the service. Record why a connection is not active where the information is available: network readiness, customer conversion, occupancy, appliance availability or relative fuel cost. The analysis should direct the next field investigation rather than assign a universal reason for non-use. A connection count becomes commercially valuable when it can be linked to activation, repeat consumption and a viable customer proposition.
How to use this research
The article uses PNGRB’s 31 March 2026 annual snapshot and October 2025 monthly MIS, checked on 15 November 2026. Rounded annual counts and precise monthly counts are not used to infer a precise time-series trend. Billed-to-connected ratios are arithmetic diagnostics, not estimates of churn, disconnection or future sales. The commercial matrix is an original analytical framework. No customer-level billing data, GA return estimates or private company performance are claimed. The IEA reference is a dated external forecast context rather than an observed outcome.
Prepared from the cited public sources. Public-document case studies describe disclosed events and analytical implications; they are not Enalyt client engagements. Commercial decisions require current quotations, controlling documents and project-specific diligence.
Sources & data notes
- S1Annual Statistical Report 2025-26 ↗
Petroleum and Natural Gas Regulatory Board · FY2025-26; network snapshot 31 March 2026; published September 2026 · Accessed 2026-11-15
Entity-reported regulatory statistics; aggregate gas table uses its own production/consumption definitions. - S2India Gas Market Report: Executive Summary ↗
International Energy Agency · Published 2025; outlook from 2023 to calendar 2030 · Accessed 2026-11-15
Forecast vintage; not current actual demand or a guaranteed outcome. - S5City Gas Distribution MIS: October 2025 ↗
PNGRB Statistics Division · October 2025 monthly snapshot · Accessed 2026-11-15
MWP targets, actual connections and billed connections are different fields.